We would like to be able to track actual vs estimated duration, as well as the variance.
ie: Duration Column 4 days, actual work 2 days, variance -2.
Duration Column 4 days, actual work 6 days, variance 2.
And be able to roll the totals up at the top of each parent task.
If a task is scheduled to take 90 minutes, but we have 2 weeks to get it completed, how do we enter those values, so we do not show our resources as 100% for the next 2 weeks.
Currently, we are setting the start and finish as the same day, and allowing for 90 minutes of duration. But I also need to add that 3rd column, Variance.
Thanks
Mark