Linked Cells Don't Match
Hello! I am attempting to link cells (Duration, Start, Finish) from a project's sheet to a master sheet. However, once I link the cells, the Finish date is different on the master sheet than what has been entered in the project's sheet.
Cells in project sheet:
Cells in master sheet:
The Finish date should be 1/2/23, not 4/26/23. Why is this happening and what do I need to do to fix it?
Answers
-
Hi kelceyg,
This could be possible because of the Project Setting in your sheet, due to this it updates the Finish date according to the Duration.
Kaveri Vipat, Smartsheet Engineer, Ignatiuz Software
Thanks,
Kaveri Vipat
Senior Associate - Smartsheet Development, Ignatiuz Software
2023 Core Product Certified
Did this answer help you? Show some love by marking this answer as "Insightful💡" or "Awesome❤️" and "Vote Up⬆️"
-
My understanding is that the duration is automatically calculated based on the Start and Finish dates? This is the only project where the Finish date is not matching what is in the project plan.
-
Hi, was a resolution found for this? Or is there a better way to link to show the date? I am running into same issue and cannot find a fix.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.6K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 468 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 64 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!