I am looking to have 2-way sync between SmartSheet and Jira. I'd like to leverage the Start and Finish dates in SmartSheet as "projected start/finish" dates, and connect over to custom fields in Jira. They are not "actual" dates, just projected. There is no system-automation on the Jira side for these custom fields.
It appears I can use Start (in SmartSheet) for a 2-way connection.
I can use Finish (in SmartSheet) as a 1-way push from SmartSheet into Jira, but not a two-way connection.
This issue is resolved if I remove "dependencies enabled" in SmartSheet. Why is this the case? With dependencies, wouldn't it also affect start date? Why am I allowed to have 2-way sync with start but not finish?