Multiple duration columns
Can you have 2 duration columns in a project plan that takes into consideration weekends and holidays? Right now the current duration column does but I need another duration column for our baselines and not sure how to get that to exclude holidays and weekends like the regular duration column does?
Answers
-
The way I would do this is by using the NETWORKDAYS function to generate the duration. At the end of the function you can identify a list of holidays to exclude, see: NETWORKDAYS Function.
Here are some other Community threads with examples that may help:
Networkday formula with Cross Sheet Reference to Holidays Sheet
Networkdays between a date and today
Cheers,
Genevieve
Help Article Resources
Categories
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!