How to overlay Team Vacation Planner into my Project Plan?

Hi,
I have 2 separate spreadsheets, a Project Plan and a Team Vacation Planner. Is there anyway I can incorporate the Team Vacation Planner with all the team members holidays into the Project Plan without having to retype all the holiday dates into the project plan?
Plus, anytime the Team vacation planner changed, this would be updated and referenced in the Project Plan? it would be great esp in gannt chart view to see the project milestones and timeline against the team availabilities.
Thanks
Answers
-
Hi @S Lim
The way I would personally do this is to create a Row Report using the two sheets as the source for the Report. Then you can Sort the Report by Date, so the Team Vacation dates are spread among your Project Plan.
Reports are automatically updated as rows are updated/added to the underlying source sheets. Here's more information: Build a row report / Working with source sheets in reports / SmartStart: Reporting
Cheers,
Genevieve