Help! Question around roadmap, resource and resource allocations, budget

Hi - Is it possible to take a proposed timeline (roadmap) and "back into it" to see if it's actually reasonable when considering the number of resources you have on the project, the amount of time they're dedicated to the project (which will differ from person to person) to see if it's possible and/or what it takes to make it possible?
Answers
-
Hi @PM_Ninja312
What I would do in this instance is set up the project plan / roadmap in Smartsheet as a gantt chart. Then I'd assign rows to individuals (tentatively) and adjust the gantt settings to show the person assigned to each task (versus the task name).
Once I have the draft set up, there are a number of ways to check through the work.
For example, I could view it through Card View to see how many tasks are assigned to each person (although that doesn't take into account Duration). I could also set up a Grouped Report, summarizing how many tasks are assigned to each person.
Here's a free webinar on Smartsheet's project settings: Project Management Fundamentals
It really depends on what your current project is and how you want to track your people. If you're looking at resourcing specifically, I would recommend looking into Resource Management by Smartsheet as well. This may help you better forecast allocation, in association with other projects currently on-the-go.
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.2K Get Help
- 431 Global Discussions
- 152 Industry Talk
- 490 Announcements
- 5.2K Ideas & Feature Requests
- 85 Brandfolder
- 155 Just for fun
- 74 Community Job Board
- 501 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 306 Events
- 36 Webinars
- 7.3K Forum Archives