How do I create a formula to show how many weeks/days out a task needs to be completed?
For example, if I have an event, or a project live date, and I want a task list that says
Task 1 is due 8 weeks prior
Task 2 is due 3 weeks prior
etc...I am new to this and cannot figure out the formula!
Tags:
Answers
-
Two options:
=Due@row - TODAY() - Will return total number of days
=NETWORKDAYS(TODAY(), Due@row) - Will retun total number of working days
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!