RAID log linking to a sheet (2-way)
Hi! I'm trying to determine if there is a way to link line items in my project plan (sheet) tot he RAID log. As I understand, cell-linking would only allow one way transmission (from project plan into RAID). Is there a way to link the cells where they can be updated in either the RAID or the Project Plan Sheet?
Thanks!
Answers
-
The only way to create a two way link would be to use a report in which case the structure may look a little off if you are referencing two separate sheets for it.
I personally would have them update the RAID log and then surface the most recent entry on the Project Plan.
-
Thank you, I thought there may have been functionality I was not aware of. Appreciate the prompt response!
-
Happy to help. 👍️
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.4K Get Help
- 364 Global Discussions
- 200 Industry Talk
- 429 Announcements
- 4.4K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 128 Community Job Board
- 446 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 284 Events
- 35 Webinars
- 7.3K Forum Archives