I am filtering specific tasks based on resource, sub-system, Function etc.
The filters are working fine, however I would like to see the associated parent tasks.
So if tasks from level 2, 3, 4, ... are shown, I want to see their parent tasks shown up to level 1 or 0.
Similar to how MS Project does.