Double Dependency
If I have a task that starts when one task finishes, but needs to finish at the same time as another. Is that possible in Smartsheets? when I include a SF with one Task, and FF with another it calculates a (1) day value and finishes with the task associated with FF
Answers
-
Hi @andrewrjohnson!
Durations and predecessors are a confusing logic puzzle. I think the challenge is that the duration is defaulting to 1d, so Smartsheet is trying to calculate the best start/end date with a one-day duration to meet the predecessor logic.
It might help to think about it another way, and enter the actual duration required to complete Exhibit B.
If it's truly one day, the start and end date of 2/14/23 is accurate. We've told Smartsheet that Task 3 has to finish before Exhibit B starts, and Task 12 needs to finish for Exhibit B to finish. Logically, 2/14/23 is the correct start and end date if the duration is one day.
If you change the Exhibit B duration to 5 days, it calculates a start date of 2/8/23 and end date of 2/14/23, which makes sense.
I hope that helps!
www.linkedin.com/in/juliefortney-pmp-smartsheetpartner-lssblackbelt
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.5K Get Help
- 367 Global Discussions
- 202 Industry Talk
- 432 Announcements
- 4.4K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 128 Community Job Board
- 447 Show & Tell
- 29 Member Spotlight
- 1 SmartStories
- 285 Events
- 36 Webinars
- 7.3K Forum Archives