Card View Sub-tasks: rearranging and moving sub-tasks
Is there a way to rearrange sub-tasks under a card once they have been added? I currently cannot do this.
Is there a way to pull a sub-task from under a card and move it under another card?
These 2 features would help a lot!
Answers
-
Hi @Rhythm
- The order of sub-tasks from within the Parent / top-level tasks is based on the order of the rows in Grid view. You can adjust the placement by changing the order of child rows in Grid view!
For example, if these are my two Child rows:
I can change to Grid view and adjust the row placement, moving Child TWO above Child ONE:
This then adjusts the order in the card:
2 . In regards to moving tasks from one to another, you can do this again in the Grid view, by changing the location of the child row. (Moving it under the correct Parent or top-level task).
See: Keep cards organized with subtasks and Hierarchy: Indent or Outdent Rows
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
-
Thanks Genevieve! That'll save me hours haha
-
@Genevieve P. Has there been a feature request submitted to allow the subtask to be reordered under the parent in the Card View so you don't have to switch to the Grid or Gantt view? If not, let me know and I'll submit. thanks!
-
I haven't seen that as an Idea posted yet, no! Please do submit the idea so others can vote on it 🙂
There is an Idea regarding Sorting, but not specifically re-ordering under Parents.
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives