My duration roll ups for child/parents are not working as expected. Can anyone advise of things I could try to resolve why only one parent has a duration total?
Hi Paul,
Start with checking your Project Settings (Right-click on any column and select Edit Project Settings).
Edit: You must have durations and dates for the parent to show the total duration.
Did that help?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I had the project settings on, but turning off and then back on worked!
thanks
Great!
Happy to help!
Andrée
I'm trying to create a formula that will output a Product category. Below is the formula and I've provided a screenshot of the columns involved. =IF(AND(Folder1 ="default", [Cost Category]1="Printer : Plex", ISNUMBER(FIND("Color",[Cost Option]1))), "Color Impressions", If(AND(Folder1="default", [Cost Category]1="Printer :…
Hi All, I have a project plan with a column called "Owner" that has a column type of contact list. The contacts are from multiple companies. It's a large project plan. I have created columns that have a column type of checkbox. I want to check the box if the owner is from a certain company (which can be determined by the…
Hello, I am trying to use JOIN-COLLECT to populate a cell with a contact by pulling from another sheet. However, when I use this formula it populates the cell with the name of the contact as a text string, but does not populate the cell with the contact itself. Both the column of cells being populated and the column the…