My duration roll ups for child/parents are not working as expected. Can anyone advise of things I could try to resolve why only one parent has a duration total?
Hi Paul,
Start with checking your Project Settings (Right-click on any column and select Edit Project Settings).
Edit: You must have durations and dates for the parent to show the total duration.
Did that help?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I had the project settings on, but turning off and then back on worked!
thanks
Great!
Happy to help!
Andrée
Hello, I deal with a lot of batch/lot numbers that are automatically generated and start with leading zeros (e.g. 000012345). I'm trying to create a column simply to count the instances of a lot number within the column in order to quickly identify duplicates. The formula I have is =COUNTIF([Lot Number]:[Lot Number],[Lot…
I have a formula in a Smartsheet that will show the last step date completed in one column and then another formula that will show the next step to be completed. The issue I have run into is that if 2 steps are completed the same day, SS is only picking up on the first one and showing the 2nd one as the next step to be…
Hi all - i am building a monthly dashboard with separate columns for each month's status, key takeaways, and next steps. I am wanting to build an automation that says for example: 'your {{current month}} status update is due, your last {{last month}} update was {{status color}}. Please be sure to indicate your key…