Is it possible to send an automatic Approval Request right after an automatic Update Request was filled in.
Hi,
Yes, it is. We need to have something trigger it. Maybe a field that is empty before the update request is sent and then information is added to that field, and that could trigger the Approval Request.
Would something like that work?
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Hi
Yes, I concur. This is possible, it is all about getting the conditions that trigger the alert correct.
The outcome of an update request can be the trigger in an approval request.
Kind regards
Debbie Sawyer Consultant & Training Manager
Smarter Processes mean happy people in successful businesses
Is there way to make the trigger automatic, or to put in column that only shows up when it is requested updated? Can anything be done with the update request status?
Hi @Janneh Wright
Not sure I follow.
Can you describe your process in more detail and maybe share the sheet(s)/copies of the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@workbold.com)
I hope that helps!
Be safe and have a fantastic weekend!
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…