Hi there, i would like to start an activity 10 days before either activity A OR activity B starts. How should i define the predecessor? BR Marco
its based off of row numbers. So if A was on row 1 and B was on row 2 you would put
1-10,2-10
exactly like that inside of the predecessors column
Hi Marco,
You can have the same predecessor for more than one task, however there currently isn't a way to define an OR criteria. Please feel free to submit a Product Enhancement Request to let our Product team know that you'd like to have this functionality in Smartsheet.
To represent a period of inactivity or overlap between the predecessor and dependent, you can use lag time. More information on this can be found here: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Hi L@123 and Alejandra
Thank you for your answers. I think I didn't express myself properly - excuse my French
In other words… “Activity C” should start 10 Days before Activity (A or , depending on which Activity starts FIRST! Example “Activity A” starts on May 1, 2019, “Activity B” starts on June 1, 2019. So “Activity C” is scheduled to start on April 20. Maybe you have an idea how to solve this problem. Thanks a lot in advance! Marco
How can I delete old sheets I no longer use from my account?
I'm trying to display a task progress chart showing "complete", "late", and "not complete" in my dashboard and for some reason the chart will display as a column chart but it won't display as a donut chart even though I'm referencing the same report. I'd prefer to display as a donut chart as I think it looks better and is…
Hello, I am trying to create a chart widget in my dashboard, but I keep getting "Selected data cannot be charted. Please select a new range." error. The report I am using is already summarized in numeric value. What is funny is I have report that I created a chart widget in another dashboard, and when I use that same…