We have created a sheet which has a start date and a due date.
I would like to have the status column change to overdue once the due date is past the current date.
If someone would be able to help me that would be greatly appreciated.
Thank you
Dave
Hi Penny,
Try something like this.
=IF([Due Date]@row < TODAY(); "Overdue")
The same version but with the below changes for your and others convenience.
=IF([Due Date]@row < TODAY(), "Overdue")
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Did it work?
Hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
I'm trying to create a graph chart that captures monthly count of records by divisions (Northeast, West and Central) that should be stacked with a legend displaying each by different color like a presented in Excel. When I attempt to duplicate the process in Smartsheet I receive the following results. In Excel, I created…
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…