I want to populate the % Percent field with 100 when the Actual End Date is entered. I tried this formula but I get an error.
=IF([Actual End Date]@row > "0", "100", "0")
Any suggestions?
Hi Dee,
Try this.
=IF(NOT(ISBLANK([Actual End Date]@row)), 1)
Hope that helps!
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
To add because I can't edit: Have a fantastic week!
Thank you and it works when I turn off % Complete in Project Settings. But then it wont calculate overall project % complete. I am stuck.
Happy to help!
Unfortunately, you can't have both.
You'd have to disable the automatic % Complete feature and add manual formulas instead.
Would that work?
Another option could be a third-party integration like Zapier or the Smartsheet API. Is that an option?
I am getting blocked with edits again as well... -_-
Yes, i get sometimes now as well.
It's back!
HAHAHAHAHAHAHAHAHA!!!!!!!!!!!
Trying to create automatic sequential ID numbers based on the date to ship and where the sample goes. Have a general auto numbering Row ID, have (thanks to reading other questions and responses) figured out how to designate a year. Now I would like to number the Internal (INT) shipments separately from the external…
*IDs have been omited for privacy but there are values in the column I need to bring in the Week # values from the Master Tracker - 2026 sheet into the Week-Over-Week Modified sheet. The group and APC ID need to match. There is a potential of duplicate APC values which is why I need the group to be a criteria as well. I…
I have one sheet that is tracking PTO where a user has entered the days off. The form allows them to enter a start and end date for their PTO and enters a single record into the sheet. I have a second sheet that I am looking to pull that data into, but there is only one record per person (column in this sheet where the…