I want to be able to use a dependency like "either/or" instead of "and"
ie: Task 3 can start after either Task 1 or Task 2 is finished, but does not require both tasks to be done.
Is this possible?
=if(or([Task 1]@row = "Finished",[Task 2] = "Finished"),1,0)
Thanks for the reply, but this seems to be saying "if task 1 is complete, task 2 is also complete" but that wouldnt be the case.
Task 1 and 2 wont be completed at the same time. But one of them needs to be done before Task 3.
I misunderstood, you mean how to set the predecessors on a project sheet then right?
Yes. I can make it use both predecessors, but I want it to use one *or* the other.
Someone may correct me if I am wrong, but I am fairly confident you are unable to do that currently in smartsheet. There is not mention of it in the official documentation. I recommend submitting a product enhancement request via the link on the right side of the community webpage.
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
I'm receiving this message every time I try to open my sheets. I'm the only admin user. I have already performed proper troubleshooting, such as clearing the cache, logging in incognito, and logging out and back in, but the issue remains unresolved. It's been a few days, and I'm unable to track our projects and this…
I’ve created an automation that generates a document and forwards it to the individual specified in a cell. The line item also has several additional attachments associated with it. Is there a way to include those attachments with the generated document?
I have an automation set up that copies a row to another sheet each day. The automation itself works correctly, but the problem is that it copies the formulas rather than the values, which causes the formulas to break and return errors. How can I configure it to copy only the values instead of the formulas?