Hi, which formula can I use to calculate the expected Progress (depending on the current date)?
Thanks
Could you give more details and share some screenshots?
Hi Paul,
I have the Start Date, End Date, Duration (days) and the Progress given by each responsible. From this Information I would like to calculate the expected Progress, how shall the Project must be going on an specific date.
For example:
I have a Task with 10 days as Duration. by the second day the Progress completed is 20% (that means is running accordingly to plan) and by the third day, the Progress is the same. That means that by the third day the Project has already a delay.
So I would like to know which formula can I use to find out this expected or planned Progress and then I can be able to make a comparison against Progress completed and create alerts if neccesary.
Thanks.
If you create a [Projected % Complete] column, you can enter this formula into it...
=(TODAY() - [Start Date]@row) / ([Scheduled End Date]@row- [Start Date]@row)
This will give you how far into the scheduled time you are for whatever today's date is. You can then build your alerts off of whether your actual % complete is less than, greater than, or equal to where you should be (projected % complete).
To show the projected finish date based off of the current progress and the start date, create a date type column [Projected End Date] and insert this formula...
=[Start Date]@row+ ((((TODAY() - [Start Date]@row) / ([Scheduled End Date]@row - [Start Date]@row)) - [Actual % Complete]@row) * ([Scheduled End Date]@row - [Start Date]@row)) + ([Scheduled End Date]@row - [Start Date]@row)
Thank you!
I have a similar request: I would like to see how the projected end date of a task will impact the overall projected end date of the project taking the predecessor relationships into account. Any ideas on how to do that with a function or in a dashboard?
Date Report Partner CBO Name 01/12/25 Children's org 05/15/25 Foodbank 08/30/25 Children's org 09/11/25 Chamber 11/25/25 Digital Bus 08/21/24 Digital Bus South 01/15/26 Children's org 01/12/24 Foodbank Sister 02/15/24 For the children org 07/01/26 Digital Bus #2 08/05/26 Family Center 12/01/26 Family Center I am trying to…
I am trying to get the passenger count per month per year, and I can't seem to get the formula correct. I need to add the number of passengers for each month per year. If anyone could assist me with this, I would greatly appreciate it. Thanks!
I need to edit a large sheet that has a lot of predecessors. I need to delete one row and move another. when I make the changes the predecessors for proceeding lines are not correctly displaying the dates correctly. Need help.