Expand / Collapse all is not an option on my primary nor any of my parent rows. Why?
This is probably because you moved the column. I would check each of your columns until you do see the options, and that column is considered your primary column.
I have renamed and moved that column many times in my history of Smartsheet. It's really easy to lose track of as your designing sheets. Our best practice is to make sure that the first column always stays the first column and you move the data as necessary to other columns if you change your design in the process.
Hi,
Expand / Collapse all is only available when you right-click (or click the menu in the column) on the Primary Column name.
Hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Andree - you have just saved me constant hours of manually expanding and collapsing indented rows - I knew there must be a way 😁 Thanks
Hi @Garry Lofberg
I hope you're well and safe!
Glad to hear that it was helpful for you as well!
Be safe and have a fantastic week!
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
If the option exists in the menu to collapse, this means that it should also be available in the functions list otherwise how can one do it programmable?
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…