How to set the start date on a given day of week after predecessor completes
If I have a task that can only happen on a Tuesday (e.g. that's when an approval committee meets), and all the predecessors are scheduled to complete the previous Thursday, how do I schedule the task to start on the first Tuesday after the predecessor completes?
Tags:
Answers
-
Hi @mvanderv
You can add Lag Days to dependent tasks by adding that number to the Predecessor cell: +2d
See the bottom of this Help Article: Work with Duration and Predecessors
Cheers,
Genevieve
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- 10.7K Get Help
- 63 Global Discussions
- 69 Industry Talk
- 385 Announcements
- 3.5K Ideas & Feature Requests
- 55 Brandfolder
- 125 Just for fun
- 50 Community Job Board
- 464 Show & Tell
- 40 Member Spotlight
- 44 Power Your Process
- 28 Sponsor X
- 234 Events
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!