I am tracking the health project status between meetings, so I have a "Current health" (Overall Health) column and a "Last meeting health" (Last PRC Health) column, right now I am doing it manually which is very time consuming.
Is there a way I can copy and paste a value based on a specific date? or maybe manually triggering the workflow.
Here is what I would like to do, any ideas?
- Click on the "Automation" menu at the top of your Smartsheet and select "Manage Workflows".
- Click on "Create Workflow" and select "Update Row".
- Set the trigger for the automation. Since you want this to happen every Wednesday, you can use a "Date-Based Trigger". Set the "When" to "Every Week" and select "Wednesday" as the day of the week.
- For the "Action", select "Copy Cell Data". In the "Copy From" field, select the "Overall Health" column. In the "Copy To" field, select the "Last PRC Health" column.
- Click on "Done" to save the automation.
Now, every Wednesday, the automation will copy the data from the "Overall Health" column to the "Last PRC Health" column.