I want to track how long an open task is delayed on a project
Hello,
You might be interested in using the baseline method to track planned vs actuals: https://www.smartsheet.com/blog/quick-guide-mimicking-baseline-functionality-smartsheet
Hi,
By how long you mean:
How much diff there was from the initial due date?
or
If a task is not completed, how much time past from the due date (meaning Today - Due date)?
How long has past since a task is considered delayed (time that past since status was changed to "delayed", etc.)?
or, something else?
Sorry, I was out of the office. I would like to track: If a task is not completed, how much time has past from due date and also track due date changes (the difference between the original due date and new due date) open task only.
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…
Hello team! Hope you all are having a wonderful holiday season. I am trying to set up an automation that will send an email reminder one time when Next Update Date = 60 days, then another automation at 30d, etc. The key is I only want it to send the reminder one time when Next Update threshold is reached. Is this possible?…
Has anyone found a workaround for sharing Smartsheet reports externally without giving access to internal data? I currently have to download the data and transfer it onto excel to create a pivot table for our client and I want to find an easier way to do so. I also already create a dashboard for our client, but I wanted…