I would like to create a milestone where it is within a timeframe I decide to setup. For Example if I put the Start Date as 5/15/18 and a target date of 5/23/18 how can I go about doing this so we can see a milestone.
Milestones are created by using 0 in the duration and having a start date.
https://help.smartsheet.com/articles/516406-creating-a-milestone
Hi Justin,
Further to Mike's solution, you could link the milestone to your task using the Predecessors column. This way your Milestone would shift when the Finish (Target) date is updated.
Kind regards,
Chris McKay
Thank you for the information
Thank you for the follow up information
Great suggestion Chris. I hate it when the tasks move but the milestones don't.
We want to implement single-sign-on at work and have received approval. However, our IT department wants all external partners to have/use Mayo credentials to log into Smartsheet. Not all of our external partners ever set foot on our campus and don't have our company credentials. I have a couple of questions. Has any other…
I can create a Chart in Dashboard from sheet well but from Report is not working now. I just try with simple Report (just contain 2 column Primary and Number) but cannot make the chart. Is there any changes recently right, because I haven't worked with Smartsheet dashboard for a long time and I remembered that I could do…