I would like to change a symbol cell based on the status of a predecessor completion status i.e.
"If a predecessor completion status is 100% then the status of this raw should change".
Hi Shanon,
You can do this by creating an IF formula in the symbol column. To get a better sense of how this works, I recommend taking a look at this blog post:
https://www.smartsheet.com/blog/support-tip-automate-RYG-balls
There are also a few posts here in Community with specific examples that you can draw on.
https://community.smartsheet.com/discussion/automate-ryg-project-tasks
https://community.smartsheet.com/discussion/if-and-formula-rgy
Happy formula building!
-Gwyneth
Sorry to be the bearer of bad news, but despite the tutorials/threads linked to above, the answer is no.
There is no way to reference the values in the Predecessors column in any meaningful way.
An IF statement in the Symbol column will only be useful if your tasks are Children of the Predecessor. There is also the added complexity of SS, FS and FF relationships to be considered.
Building nested IF statements with additional identifier columns et. will make a complex web of formulas that will almost certainly fall over in practice.
Kind regards,
Chris McKay
Apologies, I didn't look carefully enough at your request Shanon—it's more complex that my solution solves for. Thanks for chiming in Chris.
Regards,
Gwyneth
Hello! I am attempting to create a dashboard widget that shows me how much budget we are spending in each segment, and in what category. The source sheet contains these columns… "Budget" - text/number column "Category" - dropdown list (restricted to list values only) "Segment" - dropdown list (allows multiple values per…
How can I change the value in one row based off of information in that row and information in a predicessor row
Hi there, I have a project where in the project plan, based on the start date selected for a task, I'd like Smartsheet to reference another sheet (which is the table of Sprint, Start Date, Proposed Completion Date, Sprint Label) and populate the Sprint Column with the correct Sprint Label). So the formular should check…