I would like to create a milestone where it is within a timeframe I decide to setup. For Example if I put the Start Date as 5/15/18 and a target date of 5/23/18 how can I go about doing this so we can see a milestone.
Milestones are created by using 0 in the duration and having a start date.
https://help.smartsheet.com/articles/516406-creating-a-milestone
Hi Justin,
Further to Mike's solution, you could link the milestone to your task using the Predecessors column. This way your Milestone would shift when the Finish (Target) date is updated.
Kind regards,
Chris McKay
Thank you for the information
Thank you for the follow up information
Great suggestion Chris. I hate it when the tasks move but the milestones don't.
Greetings- I have a drop-down column where a staff member is emailed (request an update) if a row is marked as "assigned". If row 1,2,3 are assigned to the same staff member within a few mins, that staff member receives 1 email rather than 3 separate emails. We want each row to be a separate email so they can mark that row…
All of the automation workflows on all our sheets are "missing". This is what we see when we click "manage automation workflows" We're also unable to create new workflow. Smartsheet Gov Status shows no issues with workflows. Is anyone else experiencing this issue?
Hi. I have been the System Admin for the past 2 years. When I came into this role, I added our logo under the setting in Branding & Personalization. Our logo has now changed and I need to update it. However, when I go to Branding & Personalization the only options I have are Profile Visibility and Working Days. Did…