I would like to add up all the action items on my Action Item log that are Past Due so I can show this on my project dashboard. How do I construct the COUNTIF statement to achieve this?
Thank you from the newbie!
I don't use COUNTIF, only COUNTIFS
https://help.smartsheet.com/function/countifs
column references are like this:
[Column Name]:[Column Name]
something like
=COUNTIFS(date-column, @cell < TODAY())
should get you started.
Craig
I'm trying to create a formula that will output a Product category. Below is the formula and I've provided a screenshot of the columns involved. =IF(AND(Folder1 ="default", [Cost Category]1="Printer : Plex", ISNUMBER(FIND("Color",[Cost Option]1))), "Color Impressions", If(AND(Folder1="default", [Cost Category]1="Printer :…
Hi All, I have a project plan with a column called "Owner" that has a column type of contact list. The contacts are from multiple companies. It's a large project plan. I have created columns that have a column type of checkbox. I want to check the box if the owner is from a certain company (which can be determined by the…
I have an automated workflow set up to run weekly and request an update when the project is in certain statuses. The automation only ran once and now it's not working even though I have it set up to run weekly. I need help troubleshooting why this isn't working.