-
At Risk Formula Unparseable Error
I am trying to build a nested at risk formula based on the following triggers. -End date is today and Status is not complete it will trigger -There is not enough time between today and the end date for the duration period left. So, if duration minus % complete is 4 days. and the period of time between today and the end…
-
How can I compare two cells in a cross sheet reference?
Hello, I have a COUNTIFS formula (below) that returns the number of items that pass all the tests. Basically, count an item if it's unique id is not blank, it's % complete is 100, and the risk area is Antiboycott. This formula works beautifully. =COUNTIFS({ExportUniqueID}, NOT(ISBLANK(@cell)), {ExpComp}, @cell = 1,…
-
Different types of zeros?
The formula below is creating multiple "zeros". See pictures. What am I missing? =IF(Balance@row = "ERROR", "ERROR", IF(Balance@row = "TBD", "TBD", IF(Balance@row = "DEDUCT", "DEDUCT", ((SUM(Jan@row:Dec@row) + SUM(CHILDREN(Jan@row:Dec@row))) - (((SUM(CHILDREN([Contract Amount]@row), "Change") + ([Contract Amount]@row)) -…
-
IF(OR with RYGG
I would like to automate a RYGG column, assuming that my team is entering there own start and finish dates but due dates will be created by senior staff. Yellow=In progress Red=Overdue Grey = Not started Green=Completed So IF start date is before due date, Yellow or if Finish date is before due date Green, etc. An…
-
Getting #INVALID DATA TYPE using IF(AND and IF(OR together
=IF(AND([Logo Attached]3 = 1, [Lobby Sign]3 = 1, [Column Sign]3 = 1, Mailbox3 = 1, "Green"), IF(OR([Logo Attached]3 = 1, [Lobby Sign]3 = 1, [Column Sign]3 = 1, Mailbox3 = 1), "Yellow", "Red")) Formula above. Would like to display green ball when all checked, Yellow when some checked, Red if none checked. Can't figure out…
-
Counting overdue tasks from a lot of project sheets
Each project sheet has basically an identical structure and each line item is assigned to a specific person/user (Contact list). There are approximately 300 lines per project sheet. Each user has a report that shows only the tasks assigned to them from all the source sheets. Previously, we had a dashboard that showed each…
-
Add new row, calculated field not updating
I have a sheet that uses Hierarchy (on month) and is displayed in descending sort order. I have one calculated field that should be automatically calculated when a new row is added. When the person who will be entering data adds a new row, they are using "Insert Above" to add the row. The calculated field is not updated.…
-
VLOOKUP plus a Dropdown selection???
I don't think this is possible, but thought I'd ask here. I have a situation where I would like to look up a value in another worksheet if the the value in a column adjacent to the lookup contains "DMP". I know how to write that formula, but if the value does not contain DMP, then I don't want the lookup at all, but want…
-
If 'Submit Date' is before the 20th of current month, Set 'Payment Due' to last day of month
Hello! Creating a sheet to help with Accounts Payable process to external providers. External providers will submit their invoice and payment details into a form that feeds into this sheet. Would like the formula to determine when that invoice is set to be paid, depending on the submission date. The formula in words.. If…
-
Equation help
Hi all, I'm not very privy with formulas, but am attempting to learn. I'm working on keeping track of square footage production based on "in progress" or "completed" in a manufacturing setting. There are 6 different steps to each unit produced (on different lines, see screen shot), and I'm trying to figure out a way to…