Design Error for Resources Allocation - Percentage vs hours/days/weeks
Edit - I may have been a bit harsh calling this a design error, I do see cases it would be easier choosing percentages for resource allocation instead of hours/days/weeks - but making the latter an option would be an amazing improvement. The current design seems relevant for a projectized organization with dependables and…
-
Email signatures
It would be great to see a feature that when we email a row or send an update request, we have the ability to add a branded email signature. Does anyone have a solution to this? Thanks, Lucy
-
tracking Project by the hour
I have started a small project shedule for a job that will take around 72 hours to complete total but with multiple subs having to start and finish at certain times to hit that deadline. how do i change the calendar on the Gant to #1) just show me the 3 day assigned to the task #2) break each day down to a 24 hour time…
-
Filters
Is it possible to add a field in the Filter to sort a to z. I would like to sort open items and by what is the nearest due date. Right now it's a 2 step process. Thanks.
-
Parent Row Rollup
Is there a way to rollup values of a custom column to a parent and other hierarchical parents without using the SUM function in each parent row? For example: I added columns A, B, and C. Column C = A * B. Is there a function or some other way to sum up column C to a parent row? Or do I need to use the SUM function in the…
-
Smartsheet Slow Response Time
The more rows and columns a smartsheet has, the slower its response time. It other words, I am constantly using smartsheet with thousands of rows and columns. As a result, I am constantly waiting for your servers to process and save my work. When can we expect to see better response time? I've posted an image for you to…
-
Contingency duration based on predecessors
I was wondering if it is possible to create a task whose duration is determined by two predecessors, one from backward planning and one from forward constraints. I would like to use this, among others, to show dynamic contingency periods in my project. Let's take the simplest example, a project with the following three…
-
If NOT complete, change end date to TODAY()
Hi I'm trying to automatically increase the finish dates of tasks not completed, that were due for completion before today, to today. Is there any way to do that? Any help would be really useful
-
Highlight Changes with a unique color, shade, or pattern for each user
I would like to submit an enhancement request for the Highlight Changes feature. The tool currently shades cells with a background color if a change has been made in the last seven days. Unfortunately, the same color is used for changes performed by everyone. I'd like to request the ability to customize the background…
-
Form function for SmartSheet
Hi, I have smartsheet to record each building general meeting info, such as building manager, meeting date, building name. In each meeting, we need to prepare meeting supplies (there are around 30 items, such as pen, projector, binder..). I would like to use smartsheet "Form function". Then link is created and I can send…