-
Precedents no longer working when copying the sheet
I have a project sheet that has worked perfectly for about 10 months. It has lots of dependencies already set up. I made a copy of the sheet and removed all of the dates (highlighted them all and deleted). I have changed the names of some of the rows but the duration of every task and it's depedecies are still there (which…
-
Changing the Fiscal Week from January to July (or any other month) does not affect the Timeline week
I am trying to view my Sheet in Gantt view, tracking top row by month and second row by week. This works fine, except my company's fiscal weeks are offset. I changed the settings modifying start of fiscal week to July, but the view on the Gantt didn't change. Same result using any of the other available months as start of…
-
Gantt view format preferences
How do i set the preferences on the gantt area view format? I'd like to remove the label which repeats the task name and perhaps toggle the dependency arrows on/off. Thanks
-
What does ''deadline'' do?
So I entered the deadline for a summary task, but it does not seem to do anything except being entered. It's not visible in the Gannt, nor does it stop me from dragging anything beyond the deadline. What am I doing wrong? Thanks!
-
Top Level Task Colors
I am trying to figure out if I can change the colors of the top level (roll up) tasks. It would be great to have a default for this in the "colors/logo" settings.
-
Fixed duration in the Gantt chart
Hi all, I'm evaluating duration time of every tasks. In the sheet, I set a duration time, a start date and the end date is adjusted accordly. If I want to change the start date, the end date will be updated and vice-versa. It's fine. However, in the Gantt chart, when I'm touch a gantt bar to change the task start, it's…
-
User form- input with dependents?
Hello, I have a project template that I would ilke to use to put a project on a master schedule. I would like to fill in this template with a form, while it adds the item to a master schedule. Can I create a form that has rows with children dependents? Thanks, Harrison
-
Web form to be input to a project schedule with dependents
Hello! Is it possible to have a web form, such as input onto a project sheet with dependent children rows (that you have to hit a + or - sign for such as: I want to have the form bascially kick off a standard project management list. Thanks! Harrison
-
Question regarding lag times
I am using predecessors in my spreadsheet and need some assistance with lag times. For example, one task is to sign the contract with the meeting planners (we do that in November)--that's line 12 in my sheet. Our first payment is not due to the planners until June of the following year. If I put line 12 in as the…
-
Change colours of block out dates on Gantt chart
Hi in the dependancies I have included the public holidays for our organisation. They are "blocked out" in a very light pink colour. Is there any way of changing the colour to make it look more obvious?