Question regarding lag times
I am using predecessors in my spreadsheet and need some assistance with lag times. For example, one task is to sign the contract with the meeting planners (we do that in November)--that's line 12 in my sheet. Our first payment is not due to the planners until June of the following year. If I put line 12 in as the…
-
Change colours of block out dates on Gantt chart
Hi in the dependancies I have included the public holidays for our organisation. They are "blocked out" in a very light pink colour. Is there any way of changing the colour to make it look more obvious?
-
gantt chart export
in the title, everything is said. need help please :) don't know how to export to have my gantt chart on word, that would fit the landscape page but still visible cheers for any help
-
Recurring Milestones in Gantt Chart
Hi - I'd like to create a recurring milestone in a gantt chart. Do I need to create multiple activities on the list view or is there a formula that will generate a recurrence for a single activity? Thanks!
-
I want to add sprint into my agile project plan
How do i add extra sprints?
-
Gantt dependency Start/End Dates not populating?
I have a Gantt Chart with dependencies enabled. When I shift the entire start date of the project all the dates shift appropriately so I believe it's working well. I've just inserted a new row and assigned a Predecessor Row and Duration. The bar appears to the right and dependency lines are drawn. However the Start and End…
-
Uncompleted tasks can't start until today
I' ve just started trying to use Smartsheet as a project planning tool. I have created a Gantt chart for my project, and put in the resources. Where tasks are fully or partly completed I have put in the % Complete figure. The system does not seem to have adjusted the start and finish date of tasks that are not 100%…
-
Tracking Hours in a Day
Hello Fellow Smartsheet Users, I am looking to track hours in a day to maximize bandwidth per employee (OCR Racing & Building Obstacles). Unfortunately, Smartsheet doesn't have the ability to track hours in a day and to accurately display this in a Gantt Chart so I am looking for recommendations/tips, best practices, etc.…
-
How to disable hour for duration?
Hi Everyone, I basically only use day as duration and don't need hours as time interval. I found it was kind of annoying when I drag the bar in Gantt Chart to adjust the duration, becuase it is based on hourly increment. I have to move the mouse very carefully to locate the start or end of the bar at the day but not hour.…
-
baseline - actual dates
This post is in regards to this post below. I would like to get in touch with Jeremy michels to see if he will share the sheets he references with me.Any help will be appreciatedThanks so muchLouise Jeremy Michels601 ptsApril 5, 2015 8:30 pm I do the added columns now. We use it for both schedule and budget reasons. If you…