-
Graphic for pipeline
Hi, I am an architect and I NEED to see all the data graphically. I am looking for samples of project pipeline graphics produced using Smartsheet. Please, post them here or send me a link. Thanks! ileana
-
Gantt moves a Monday meeting to Friday because of Predecessor setting
I have a task for a project that should be completed on Friday. The following Monday, I have a milestone (meeting) to review that task (proposal), The completion of the task on Friday is the predecessor for the milestone on Monday, but as soon as I set that predecessor, the milestone is moved to Friday too. I can't figure…
-
Set recurring tasks, meetings
How do you easily set recurring tasks and meetings in Gantt view and Calendar? Example: Phone meeting or email updates, every 2nd and 4th week of the month?
-
Créer une ligne de date réccurente
Bonjour, Je ne trouve pas le moyen pour faire une ligne avec des dates réccurentes (par exemple réunion tous les mardi à 15h ou tous les 1er mardi du mois). Merci de votre aide.
-
Will your next release have Baseline?
I am new to Smartsheet, coming from MS Project, here at new employer and I am in need of the baseline relative to the Gantt chart. Is this feature being worked on for the next release?
-
scroll in Gantt chart with magic mouse
How do I keep my scroll bars up? They always hide after I scroll, and switches pages when I swipe my hand too much on the mouse. Would like the bars to appear at all times like this:
-
Fixing the Gantt timeline to Years and Months
Hi all, Something is driving me a little crazy and I wonder if anyone could help? Our client likes programme timelines to be displayed like this: - primary heading: years - secondary heading: months This works fine until someone zooms in or out (using the +/-) buttons on the Gantt chart. When they zoom they are unable to…
-
Not possible to color Gantt bars by what parent task they are under?
I'm setting up a project with big task parents for the major parts of the project with many sub-tasks. Is it not possible to use a conditional formatting rule to make all the tasks under a particular parent a specific color?? This seems like a very basic feature but I can't figure out a way to do it.
-
Create Task Start and Finish Dates with Mouse in Gantt?
Is there a way to create start and finish dates in the Gantt chart view by simply clicking/dragging on the Gantt chart calendar? It seems the only way to initially create a start/finish date is by using the Start column and clicking on a date on the calendar that appears. This is clunky and it would be much easier to just…
-
Amount of Working Time Between Tasks
We have a desire to calculate the amount of work time between the end date of a task, and the start date of it's successor task. Before the update that included partial day durations, we were performing this with simple date arithmetic. Now, that arithmetic does not hold true, and we need to devise an updated formula to…