-
Web form to be input to a project schedule with dependents
Hello! Is it possible to have a web form, such as input onto a project sheet with dependent children rows (that you have to hit a + or - sign for such as: I want to have the form bascially kick off a standard project management list. Thanks! Harrison
-
Question regarding lag times
I am using predecessors in my spreadsheet and need some assistance with lag times. For example, one task is to sign the contract with the meeting planners (we do that in November)--that's line 12 in my sheet. Our first payment is not due to the planners until June of the following year. If I put line 12 in as the…
-
Change colours of block out dates on Gantt chart
Hi in the dependancies I have included the public holidays for our organisation. They are "blocked out" in a very light pink colour. Is there any way of changing the colour to make it look more obvious?
-
gantt chart export
in the title, everything is said. need help please :) don't know how to export to have my gantt chart on word, that would fit the landscape page but still visible cheers for any help
-
Recurring Milestones in Gantt Chart
Hi - I'd like to create a recurring milestone in a gantt chart. Do I need to create multiple activities on the list view or is there a formula that will generate a recurrence for a single activity? Thanks!
-
I want to add sprint into my agile project plan
How do i add extra sprints?
-
Gantt dependency Start/End Dates not populating?
I have a Gantt Chart with dependencies enabled. When I shift the entire start date of the project all the dates shift appropriately so I believe it's working well. I've just inserted a new row and assigned a Predecessor Row and Duration. The bar appears to the right and dependency lines are drawn. However the Start and End…
-
Uncompleted tasks can't start until today
I' ve just started trying to use Smartsheet as a project planning tool. I have created a Gantt chart for my project, and put in the resources. Where tasks are fully or partly completed I have put in the % Complete figure. The system does not seem to have adjusted the start and finish date of tasks that are not 100%…
-
Tracking Hours in a Day
Hello Fellow Smartsheet Users, I am looking to track hours in a day to maximize bandwidth per employee (OCR Racing & Building Obstacles). Unfortunately, Smartsheet doesn't have the ability to track hours in a day and to accurately display this in a Gantt Chart so I am looking for recommendations/tips, best practices, etc.…
-
How to disable hour for duration?
Hi Everyone, I basically only use day as duration and don't need hours as time interval. I found it was kind of annoying when I drag the bar in Gantt Chart to adjust the duration, becuase it is based on hourly increment. I have to move the mouse very carefully to locate the start or end of the bar at the day but not hour.…