-
Total Cost Based on Date of Task Being Finished
I am working on charting out dev tasks and need to display what our expected total monthly cost would be based on the tasks finished each month. I am struggling to find out a good way to have this either permanently displayed or easily accessible. I have tried reports but that only displays all of the costs and does not…
-
More customizable/specific sharing options
Hello all, I'm new to Smartsheet and am discovering the limitations when it comes to sharing. First, I'm surprised that sharing folders isn't possible. I understand that Workspaces are intended to make up for this but I guess what I'm lacking is the ability to choose specifically what I share within a workspace. What I'm…
-
Show milestones along a row with multiple dates
It is possible to show milestones along a single row with multiple dates per the screen set below?
-
How to have a date dynamically changed based on a value in another column?
I'd like to be able to have the dates in a column update based on the Sprint number. So, I've created a new sheet with one column with the Sprint # and a column for the associated dates. I have a column in my main project spreadsheet titled Sprint #. I'm having trouble figuring out how to tie it all together. I've been…
-
Webinar recording available: Keep Your Projects on Track with Baselines
Missed the webinar? Catch up on the recording here. Join us on June 3rd for an introduction to baselines, the newest project management capability from Smartsheet. In this webinar, you'll learn how to easily compare planned and actual project schedules, identify critical variance, and accurately report on project…
-
Actual vs target Date
Hi, Need a help if my Start Date is 05/24/2021 and end date is 07/01/2021 and in my project plan sheet say i have a task that start on 06/24/2021 and end on 06/28/2021 .However, that task is already been completed and the actual % Complete has been updated to 60% for that task i want the schedule Health should be turn to…
-
Schedule Health formula not working,
Hi, Can anyone help me with a formula i have three scenario .1 & 2. IF start date and end date % complete activity exceed the daily % completion , Status should be In progress and color the schedule health to Green 3 % complete is less than the expected work to be completed within the time frame it should be Red and status…
-
Flagging a double booked room
Hi Guys I have a tracker that my team use to manage their daily tasks. However, due to COVID there can only be a specified number of people in a room at a certain time. Often rooms have been double booked, resulting in work being delayed. I want to highlight whether a room has been double booked on a specified date by an…
-
Planned dates and actual visible on Gantt chart
I'm expecting my next project to be subject to a lot of external influences and dependencies. When faced with this challenge I like to show the original plan and the actual / newly forecast start and end dates to report upwards effectively and discuss the any slip. So in effect each activity has an "originally planned"…
-
How do I calculate the difference between 2 dates?
Trying to track variable durations of past projects and simply want to subtract the start date from the completion date... depending on which format the column is in, I get various errors. Seems like I should be able to simply subtract one cell from the other, no?