-
Will and API token for a report give access to the Sheet the Report generated from?
Hi, I have a large Smartsheet, I want to generate a row report that reduces information displayed down to a specific group. For that Row Report, if I were to generate an API token and share it to a third party, will that third part have access to the information on the original 'Grid' sheet, or will it be reduced to what…
-
Will Smartsheet roll out an enhancement adding the ability to have more that 20,000 rows per sheet?
We use Smartsheet for several data repositories to feed data into other sheets via formula. We are running into issues because of the row limit in sheets. Will you be adjusting the sheet row limit, if so when?
-
How can I make FS dependencies start on the same date the predecessor ends?
Hi everyone, I’m migrating a schedule from MS Project to Smartsheet and I noticed a difference in how FS (Finish-to-Start) dependencies behave. In MS Project, when a task has an FS predecessor, the successor’s start date is set to the same day the predecessor ends. But in Smartsheet, the successor is pushed to start one…
-
Link existing table
Hi, I have a table which is linked to database and the table would have new row add. I want a table that have the same data and I can insert a new column to calculate the data. I've found some ways: Cell linking, Report, Connect Your First Sheet to a DataTable. If I use Cell linking, I need to maintain it manually. Report,…
-
Metric sheet not available in data source
I have a Metric sheet in my workspace in which I have admin/edit access. When I try to do a Countif formula on it, the metric sheet is not available in my data source list. Does anyone have suggestions? Thanks!
-
Not able to save
Hi, Is anyone else having difficulty saving their work? I have tried different browsers, giving it time to save and even redone work. When I go to save I get an error message and then I have to abandon all the work I did. Not sure why this is happening- it happed before, but now it seems to be more frequent. Any insight…
-
Error on loading template
Good day, I need help please. I am currently struggling to open new sheets making use of existing templates, this has never been a problem before. I already tried to use 2 different browsers for this (Google & Microsoft Edge), I am still getting the same error. I am not able to do some work and falling on a backlog due to…
-
Incorrect time evaluation
Wir haben damit begonnen, die erweiterte Berichtsfunktion von RM zu nutzen, um dem Kunden anschließend einen Monatsbericht der angefallenen Stunden zukommen zu lassen. Wir wollten den Monatsaufwand mit folgender Formel auswerten: =SUMIF(Startdatum Woche:Startdatum Woche, AND(MONTH(@cell ) = 8, YEAR(@cell ) = 2025),…
-
How to "fold' up a row or section in a calendar, but not lose content
I want to be able to 'fold' up a few rows (a month) in a 12 month calendar, as we have passed those months, but I do not want to lose the content, as I will want to be able to open up the individual months later.😁
-
Smartsheet Calendar unable to update health status on source sheet
Hi, I created a Smartsheet calendar organized by Phase and then Workstream, with deliverable bars spanning duration. The goal is to create an interactive Gantt chart, which team members can update tasks on the calendar detailed side panel. The formula on the source sheet states that if At Risk is checked then Health is…