Dear All,
Can someone tell me what is the equivalent of MS Project constraints in Smartsheet. I have been reading of using Lag time but wanted to know if there is another way of doing it the same.
Many thanks,
Taru
Hello Taru,
Er du Norsk?
Smartsheet has dependencies built right in. You can use these to achieve what you're after.
If you locate the Predecessors column in your sheet, it will behave in a similar way to MS Project, with the ability to free type dependencies (e.g. 2FS + 2d, 24 etc.) or set them via the pop-up dialogue that appears when you click on the edit icon in each cell.
Hope this was what you are after.
That's a big big weak point of smartsheet not to be able to have the ability to constrain dates like in microsoft project and primavera.
Anyway we can make this view only for security purposes? We would like to prevent users from sending responses to other users by accident.
I am currently setting up an automation for people to get notified through their email, when they are prompted. But is there a way that they can reply in the email of a comment that will then go to the specific sheet. This way they do not have access to the sheet, but can just comment through email with updates?
I am extremely frustrated and disappointed with my current Smartsheet experience. I have paid for a Pro subscription, I am the owner and administrator of my account and sheets, and I have confirmed I am logged into the correct account. Despite this, Smartsheet is not recognizing my Pro subscription, and I am unable to…