Dear All,
Can someone tell me what is the equivalent of MS Project constraints in Smartsheet. I have been reading of using Lag time but wanted to know if there is another way of doing it the same.
Many thanks,
Taru
Hello Taru,
Er du Norsk?
Smartsheet has dependencies built right in. You can use these to achieve what you're after.
If you locate the Predecessors column in your sheet, it will behave in a similar way to MS Project, with the ability to free type dependencies (e.g. 2FS + 2d, 24 etc.) or set them via the pop-up dialogue that appears when you click on the edit icon in each cell.
Hope this was what you are after.
That's a big big weak point of smartsheet not to be able to have the ability to constrain dates like in microsoft project and primavera.
Hi, I am wondering if there is a solution for this scenario: I have a Data Shuttle data upload workflow to a Target Sheet that is updated when a new attachment is added. Question: is there a function/features/workaround like Data Shuttle, Bridge, or a combination of features so that if a new column is added to the Excel…
I have downgraded to business but no longer have access to my sheet,i get an error 48,get licensing? How do I fix this? This is a customer contact form so i cant recreate it as the email has been sent?
I have been given access as an Admin to edit an existing sheet but cannot edit columns. I am a System Admin. I am a paid Member. I am able to edit information in the sheet but cannot add a column.