Hello,
I am receiving an error window stating that the sheet has reached the max number of different cross-sheet references. Would someone be able to provide more insight on max level of cross-sheet references?
Thank you
Hi OBR,
Previously discussed here: https://community.smartsheet.com/discussion/maximum-number-cross-sheet-references-sheet
There are 2 relevant limits for cross-sheet formulas:
Additional information about cross-sheet formulas is in our support article.
Daniel, I have to say I'm not very impressed with the limits or the fact that the support article has still not been updated to highlight the 100 cross-sheet reference limitation.
It couldn't take more than 5 minutes for someone to amend the article to include:
Almost 2 weeks later and still no update to the support article. Someone has to be accountable for these articles being kept up to date. Really poor form guys.
I have forwarded this post to someone that I believe cares (and works at Smartsheet)
Craig
Thanks Chris for checking in. I thought I responded to your earlier post, but it looks like it may not have posted for some reason -- apologies.
The help article is now updated. For context: our support team tracks and reviews content update requests at regular intervals and updates content in a way that ensures consistency across all our articles. This is why updates typically don't occur right away. I agree that 2 weeks is a bit long.
Thanks for your patience, and please keep the feedback coming.
Thanks Craig
I have created a approval workflow for two forms. Some information needs to be pre-populated from form 1 into form 2. Can I write a code in the url link in form 2 to have the information appear on the form?
Hi,
Not sure I follow!
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@getdone.se)
I hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Hi all, Hopefully this is a simple solution that I'm just missing, but if I have a report view of a main sheet, is there a way to click on a particular row in the report and have it link to the full details available in the parent sheet? I want to be able to provide folks a simple view of everything, but reports fail for…
Hi Community, We encountered an unexpected issue with a Dynamic View today. An admin who had previously been added to the Dynamic View was found to be missing from the Admin list. We are confident that the admin was not manually removed or edited by our team. We noticed the issue at approximately 9:30 AM on Monday (UTC+8),…
Hi, This morning (UTC+8) we can not edit the data shuttle. When I go into the edit page of data shuttle it says I need to ask for access approval to continue. But I am the manager of the data shuttle. And from the sharing setting page, I can confirm that I am still in the manager list. Is this an internal server problem?…