Hi, we are planning a home construction project and are not sure of dates. Is there a way just show days without dates, and exclude Sat/Sun?
Hi,
You can plan out the project and only begin with using the duration column, but it will not show a Gantt chart (I think that´s what you're after?). You'll have to have start and end dates to be able to show the information on a Gantt chart.
Regarding the exclusion of Sat/Sun. You can set that up in the Project Settings - Dependency Settings in the Gantt view.
I hope this helps you!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Anyway we can make this view only for security purposes? We would like to prevent users from sending responses to other users by accident.
I am currently setting up an automation for people to get notified through their email, when they are prompted. But is there a way that they can reply in the email of a comment that will then go to the specific sheet. This way they do not have access to the sheet, but can just comment through email with updates?
I am extremely frustrated and disappointed with my current Smartsheet experience. I have paid for a Pro subscription, I am the owner and administrator of my account and sheets, and I have confirmed I am logged into the correct account. Despite this, Smartsheet is not recognizing my Pro subscription, and I am unable to…