Hi there,
Is there a way to auto-fill across the header? For example, if I put the very first date and then add a formula to add 7 days across until the end of the project? Or do you have to manually enter each header? I am trying to find an easier way to update template headers.
Thanks,
Jill
The actual column headers themselves (the gray bar across the top housing the column names) cannot be autofilled. You could autofill the first row, but to reference them in formulas, you will still have to use the actual column names.
Hi Jill,
Depending on your sheet structure and use case you could use a Google Sheet or Excel sheet and calculate the dates there and then import that sheet to Smartsheet.
Would that work?
I hope this helps you!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Hello, smarter friends: I'm trying to learn how to utilize automations to move certain rows to new sheets in order to explore if my larger/longer ranging goal is possible. Where I'm Currently Stuck: I can't even figure out how to create functional auto to send a row to a basic sheet. That is my immediate need. But if…
I'm having issues accessing Smartsheet in both the desktop app and web browser and continually get the below error message…I need to refresh multiple times to get it to work. And sometimes it works and sometimes it doesnt:
This just started today… For some reason, I can no longer edit fields in my Smartsheet. One I'm the owner of. I do see an icon in the upper right that says "Comment Only", but can't figure out how to change it. Here a screenshot of what I am seeing: