Connect with peers, share your expertise, and inspire what’s next in Smartsheet — from proven practices to practical how-to insights from fellow users and product experts.
Sign in to join the conversation:
I have a smartsheet that is pushing data to another sheet. Percentages complete are part of the data that is being pushed. On the source smartsheet it shows 45% for a section. On the Target sheet it shows 63% complete for the sames rows. Can anyone explain why I am getting 2 different percentage completes calculated?
If you look at your dates in a Gant view it shows that you have more of the work shown to be done in the second list. the first one the first 3 things on the list only are scheduled to take 5 days where as the ones on the bottom are scheduled to take 10 days.
I hope this helps.
Indeed it did. I have gone in and copied over the dure dates and it is not the same on both smartsheet's.
Thank you!!!
Hi, I have a very simple automation set up where if the box is checked, change the dropdown column for that row to COE Team. I tried it and it didn't work. I waited for about an hour to see if it was taking a long time but it still is not working. There is no formula involved with the automation so it would be a manual…
I was archiving critical accounting data from one sheet to another by moving the rows. This is something I've done countless times in the past decade of using Smartsheet. This time, after moving nearly 3500 rows of data, I realized none of the attachments moved with the rest of the data. I've opened a case but have had…
Hi Team Is there an update on this Community post from a year go? Issues with copying in the Windows App - Table View - Smartsheet Community I have confirmed in both Desktop and Web Applications, and on multiple browsers where the Clipboard setting in "ALLOWED", but the copy/paste CTRL-C/CTRL-V is not working. It doesn't…