I've imported a project into a project sheet and now would like to level the resources that are overallocated so the schedule adjusts to show the actual schedule if I use these resources. Is there a way to do this?
Thanks in advance,
Sue
Hello,
Thanks for your post! Currently, there isn't a feature which will automatically level out or reschedule over-allocated resources in your project, but you can submit a Product Enhancement Request using the quick link to the right. You'll want to manually re-allocate your resources according to your needs. It may be helpful to insert two additional date columns for Planned vs Actual Start and Finish dates which can be switched in the Project Settings to give you different views of the sheet. I've linked some additional resources for this below:
I hope this helps!
Isaac JSmartsheet Support
This is disappointing. Unfortunately the lack of this feature disqualifies the software for my organization. Is this on any sort of roadmap?
Hi,
Have you looked at 10,000ft?
Smartsheet presented some more details about the 10,000ft capabilities at Engage.
More info: https://www.smartsheet.com/content-center/best-practices/engage-content/better-together-smartsheet-10000ft-story
https://www.10000ft.com/
More info: https://www.smartsheet.com/content-center/news/smartsheet-acquires-10000ft-enhance-resource-management-capabilities
Speaking more broadly, with the integration of 10,000ft, Smartsheet customers will benefit from the ability to plan and allocate resources across their projects, optimize resource allocation by function or skill set, track time against forecast, and gain real-time portfolio level visibility into the status of budgets and deliverables.
I hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Hi, I currently have smartsheet and 10000ft but can not find the features that can level resources similar to MS project. Is there a leveling feature? We may have to switch back to MS Project because it is difficult as tasks move around to reallocate resources manually.
Also, is there a split-task feature because this also makes the process difficult when resources need to be shared among our tasks.
Has this been updated in recent years? I also need to level resources so a valid schedule is created. Is the only way to create a schedule to add predecessors in for each task?
Thanks,
James
Following on from James' comment, has this been updated? If not, I will have to give up on Smartsheet - without this feature it's too limited to justify its use.
All the best,
Enzo
Hi all, Hopefully this is a simple solution that I'm just missing, but if I have a report view of a main sheet, is there a way to click on a particular row in the report and have it link to the full details available in the parent sheet? I want to be able to provide folks a simple view of everything, but reports fail for…
Hi Community, We encountered an unexpected issue with a Dynamic View today. An admin who had previously been added to the Dynamic View was found to be missing from the Admin list. We are confident that the admin was not manually removed or edited by our team. We noticed the issue at approximately 9:30 AM on Monday (UTC+8),…
Hi, This morning (UTC+8) we can not edit the data shuttle. When I go into the edit page of data shuttle it says I need to ask for access approval to continue. But I am the manager of the data shuttle. And from the sharing setting page, I can confirm that I am still in the manager list. Is this an internal server problem?…