Similar to MS Project, is there a way to make tasks inactive so they show with strikethrough but do not affect the schedule/project timeline?
You will need to do some additional work. First you will need a column to designate needed vs. not needed. To get the strikethrough, you will need to set up conditional formatting that says to strikethrough if the "needed" box is not checked. Then you will need to build some automation (or build into existing) that basically that if the box is checked, include it or if the box is not checked, exclude it.
There are actually a few moving parts and options to accomplish what you need, so if you are able to provide screenshots and details on exactly how your timeline is working, etc., we could help you with a more specific solution.
Anyway we can make this view only for security purposes? We would like to prevent users from sending responses to other users by accident.
I am currently setting up an automation for people to get notified through their email, when they are prompted. But is there a way that they can reply in the email of a comment that will then go to the specific sheet. This way they do not have access to the sheet, but can just comment through email with updates?
I am extremely frustrated and disappointed with my current Smartsheet experience. I have paid for a Pro subscription, I am the owner and administrator of my account and sheets, and I have confirmed I am logged into the correct account. Despite this, Smartsheet is not recognizing my Pro subscription, and I am unable to…