I would like to know if there is a way to force a task to be planned a particular day of week (sunday in my case) ?
Saturday and sunday are not working days but for special IT operations we need to work a day off.
Thanks for your replies.
Hi Xlaurent,
Thanks for this question; even if your non-working days include Saturday & Sunday, you can still manually input a task onto a Saturday or Sunday by putting in a task with a 1-day duration manually onto that date.
If your tasks have more than a 1-day duration, you'll need to input multiple 1-day-duration tasks in order to work around the non-working day settings.
Please let me know if you have further questions on this!
Alison
Thanks for your reply.
I found another solution. I have set sunday as a working day and I put in the non working days exceptions all the sundays where we do not work.
Xavier
That's another great solution!
it's just half a solution. there should be the possebility to add addtionals kalendars or exceptions if only one kalendar ist possible.
if someone tells you, that they cant work in a certain periode, you are forced to solve it manualy.
add this to my long wishlist
I am currently setting up an automation for people to get notified through their email, when they are prompted. But is there a way that they can reply in the email of a comment that will then go to the specific sheet. This way they do not have access to the sheet, but can just comment through email with updates?
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…
When i try to send or print the timeline view instead of showing the progression bars like they do on the screen it only send the data entered and not a graph type view to print. Is there a way to do this. I am using a mac platform if that helps.