I am having my team track their time. I have a column for a start time and end time. Right now I am using military time )0 to 24 but I would like to know if there is a way to use normal time so my team can use 1pm to 3pm.
Hi Rick,
Yes, it is!
I'll get back to you when I find the post.
Look here: https://community.smartsheet.com/discussion/calculate-time-between-two-dates-days-hours-and-minutes
Hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Is there a possibility of overlapping midnight such as 8pm - 4am? Will you need to track multiple days such as 1/1/19 (time) - 2/2/19 (time)?
The single task of converting 12 hour to 24 hour is actually pretty straight forward.
You would pull the hours portion of the time using this:
=VALUE(LEFT([Time Column]@row, FIND(":", [Time Column]@row) - 1))
and use a basic IF statement to add 12 to the hours if it find a "p" in the time something along the lines of:
=IF(FIND("p", LOWER([Time Column]@row)) > 0, 12, 0) + VALUE(LEFT([Time Column]@row, FIND(":", [Time Column]@row) - 1))
.
Now that you have converted the hours to a 24 hour clock, you can use that times 60 to convert it into minutes and add the minutes from the [Time Column].
Do this to both the Start Time and Finish Time. Once you subtract Start from Finish, you'll have the total minutes that the task took.
You can then use something along the lines of this to determine how many hours that was:
=[Difference in Minutes]@row / 60
This will give you the result of (for example) 6.5 for six and a half hours. If you would rather six and a half hours displayed as 6:30, it will take just a couple of different/extra steps.
=INT([Difference in Minutes]@row / 60)
gives you the hours.
=[Difference in Minutes]@ row - (INT([Difference in Minutes]@row / 60) * 60)
will give you the minutes.
=INT([Difference in Minutes]@row / 60) + ":" + [Difference in Minutes]@ row - (INT([Difference in Minutes]@row / 60) * 60)
would give you the result of hh:mm
I have build a email validation in my sheet where entered emails from a form are entered in a contact field. another field verify the address and validades using the following formula: =IF(FIND("@xxxxxxx.com", [Student eMail]@row) = 0, 0, 1) if the checkbox is triggered (=0), then the registration is valid, and the the…
I have a sheet that has a good number of automations that populate a field based on a value changing in a cell. These same automations have been working just fine since March up until today. All of a sudden they are being triggered when there is no change to the cells in question. If I click into the cell history, it…
Hi, I'm in the midst of a Smartsheet trial and would like to understand how to set up a project schedule that uses a firm delivery deadline. I understand I could use Start-to-Finish relationships, but this disallows use of many to one predecessor relationships (multiple tasks that are gated by a single work item). I would…