Hello,
Is there a setting to set the current day to be centered in the gantt view when I open my sheet? I always have to scroll over to the current day on long projects.
Thanks,Phil
The top view is what i'd like to see. The bottom view is what is shown when I open my sheet.
Hi Phil,
There is a setting in the Project Settings > Timeline Display > Open to today's date.
Hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Screenshot added.
Does anyone know how to add multiple rows to a request? I am only seeing an option to send one row at a time. In grid, you can select multiple rows and do one row update for them all, but I can't find this option in table view. Thanks! Regina
Please help! I've tried Smartassist with no luck! I'm creating a project financial tracking template and have hit a challenge with charting. My source sheet contains one row per month and includes: Financial Month (stored as text) Actuals (Cumulative) Forecast (Cumulative) A helper column called "In Plan" that I use for…
We have 2 licenses. The HR make changes and I complete the process. She added 16 new staff members on our sheet but I do not see the entries from my side.