Is there a setting to set the current day to be centered in the gantt view when I open my sheet? I always have to scroll over to the current day on long projects.
Thanks,Phil
The top view is what i'd like to see. The bottom view is what is shown when I open my sheet.
Hi Phil,
There is a setting in the Project Settings > Timeline Display > Open to today's date.
Hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Screenshot added.
Anyway we can make this view only for security purposes? We would like to prevent users from sending responses to other users by accident.
I am currently setting up an automation for people to get notified through their email, when they are prompted. But is there a way that they can reply in the email of a comment that will then go to the specific sheet. This way they do not have access to the sheet, but can just comment through email with updates?
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…