Automated workflow Outlook email with attachments based on form responses
Hi all :)
I am trying to figure out how to create an automated workflow that will email the respondent PDF forms based on their answers. To put it into context, we will be having new providers "registering" themselves using a form where I would like to have them select which programs/software they need access to. In order for them to get access, they need to fill out program/software agreement forms (like access to a client records database). I am hoping to create a workflow that sends them a copy of the specific forms they need to sign, based on which programs they need access to.
Something like:
"[Insert Name]
Thank you for registering with our program! You indicated that you need access to Asana and Miro. Please sign the attached forms and --- back to us, so we can get you started."
Ideally, if they can reupload them to SmartSheet or have some way to send them back signed to us, it will then be forwarded to the appropriate admins of the programs/software.
Is this possible?
Re: Smartsheet Forms and Word
Also, have you explored using the Document Builder feature?
Andrée Starå
Re: outside of organization
Hi @JenaW - I think Sam's reply is still on the right track. Assuming they enter the email addresses into a field called "Email", I recommend you add a column to your sheet (not on the form) called "Domain" that parses the domain of the emails they enter. Column formula = right(email@row, len(email@row)-find("@", email@row)).
Then, use an automation to send them the copy of their response: When a row is created, condition where the checkbox was checked, and where Domain = Medline.
Hope that's helpful!
Scott Peters
Re: Why is a formula not triggering unless someone opens the sheet?
Hi @jmhoward
I hope you're well and safe!
Please have a look at my post below with a method I developed to update the sheet(s) daily.
More info:
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
Andrée Starå
Re: Why is a formula not triggering unless someone opens the sheet?
I had a similar issue and use an automation. This action will cause a virtual open/close of the sheet which will update the formulas in the sheet.
I created a column named date. Then I used automation that runs everyday at 2am. This automation records a date in the date column I created.
Re: Different Settings in Same Project Sheet
Yes! If you're using a Project Sheet with specific working days and times enabled (e.g. 5 day work week and holidays), then on the specific rows where you want it to be a 7 day work week you can use elapsed time by adding an e in front of the duration.
Here's more information: Work with Duration and Predecessors
Cheers,
Genevieve
Genevieve P.
Re: outside of organization
@JenaW exactly. However, you can directly exclude non-Medline emails in the automation, in a condition block, if you don't want to set up a formula. In the condition block you would say email contains @medline.com or whatever it is, then it would only send to emails with that domain.
If you want a checkbox still to ask if they want an email, you would add that as a question on the form, and add it to the condition block saying it's checked.
Samuel Mueller
Re: SOC2 Result
Hi
if you visit this page there is a link to request a copy of the latest SOC2 report:
Does that help?
Re: Dynamic View - details panel
Hey @jeanniesry_4,
Do any of those fields meet the following criteria in your source sheet:
- Field is from a System Column
- Field is from a Gantt End Date Column
- Field is the "End date column" in the date range display of the project settings
- Field is from a Gantt Predecessor Column
- Cell in source sheet contains a formula
- Cell in source sheet contains an inbound cell-link
- Cell in source sheet contains a Hyperlink
If any of those conditions above met the criteria, then this may be the root cause.
Ash A.