What formula to use for days remaining before due/start date?
Hello community,
I am currently a little stuck trying to figure out what formula to use for the "days remaining before conference" column. I'd like to have a number there to know how many days are left before the 'start date' of the conference.
Do I need to add a hidden TODAY column or automation? I'm still fairly new to SmartSheets and I a in the process of taking courses...lots to learn. Thanks in advance.
Best Answer
-
@laura.sandoval You forgot a single quotation mark. A common and fortunately simple mistake to fix! You need a quotation mark between "Consideration" and the parenthesis. I've added it below. It should work now!
=IF(OR(Status@row="In Progress", Status@row="Pending Consideration"), NETDAYS(TODAY(),[Start Date]@row))
Amber Eakin, MSLS, M.Ed.
Adult Education Specialist | Process Improvement Enthusiast
Answers
-
Good morning! You don't necessarily need a new hidden column. The NETDAYS formula will calculate the number of days between two dates.
=NETDAYS(TODAY(), [Start Date]@row)
If you specifically need to know the number of workdays, you could use this.
=NETWORKDAYS(TODAY(),[Start Date]@row)
In the example below, we have NETDAYS in the bottom and NETWORKDAYS in the top.
Amber Eakin, MSLS, M.Ed.
Adult Education Specialist | Process Improvement Enthusiast
-
This was so much easier thank you! I have one further question that I forgot to mention. What do I add to the formula for it to apply the formula only if the status is "In Progress" or "Pending Consideration"?
-
No problem, @laura.sandoval . Did you have some alternative you want the cell to read if the status isn't either of those?
Here's the formula nested in an IF statement with a picture below. In the row that says "Not Started," the formula calculates nothing (the FALSE part of the IF statement).
=IF(OR(Status@row = "In Progress", Status@row = "Pending Consideration"), NETWORKDAYS(TODAY(), [Start Date]@row))
If you want the column to have something, you would add it like this formula with a picture below.
=IF(OR(Status@row = "In Progress", Status@row = "Pending Consideration"), NETWORKDAYS(TODAY(), [Start Date]@row), "False Statement Here")
I hope that helps!
Amber Eakin, MSLS, M.Ed.
Adult Education Specialist | Process Improvement Enthusiast
-
I'd like it to be blank if the status isn't either of those, it says #UNPARSEABLE :( I may have input it wrong. This is the formula I added:
=IF(OR(Status@row="In Progress", Status@row="Pending Consideration), NETDAYS(TODAY(),[Start Date]@row))
Is NETWORKDAYS for work week days? I'd like it to include the weekend days too so I put NETDAYS instead. What do you think?
-
@laura.sandoval You forgot a single quotation mark. A common and fortunately simple mistake to fix! You need a quotation mark between "Consideration" and the parenthesis. I've added it below. It should work now!
=IF(OR(Status@row="In Progress", Status@row="Pending Consideration"), NETDAYS(TODAY(),[Start Date]@row))
Amber Eakin, MSLS, M.Ed.
Adult Education Specialist | Process Improvement Enthusiast
-
It worked thank you!!!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!