Hi guys,
I am setting up a dashboard and trying to collect data for it. I would like to show average duration for projects, if possible. For example, I have the columns below. Is it possible to create a formula that will tell me an average length from received to approved? Or do I need to add an actual “Days” column into the data base?
Answers
-
You could add a helper column Duration with formula = DRE Approval Date - DRE Received Date (for example with first row of data= 11/22 - 11/16 = 6)
Then make a summary section at the top of the sheet and add formula =AVERAGE of the Duration column. That would yield an average for all rows/projects
-
Thanks, that is helpful. Is there a way to account for work days in the Duration helper column?
-
look at NETWORKDAY AND NETWORKDAYS functions
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!