Using Duration to set predecessor task in advance of a fixed date/task
Greetings,
Can anyone explain how to use a predeccesor/successor relationship in the past on a schedule?
I have a fixed task 'start date' where the task sets the schedule for the sheet.
I want to have a task start -6 weeks from the 'start date' task, but dont know how to do this - when i try and edit the predeccesor, it will not let me use '-6w' in the duration column or as a 'lag time'.
Thanks for support/advice
Answers
-
Greetings @doram_coastalcraft,
To have a task start 6 weeks before the start of another task, use the following notation in the Predecessor column of your project schedule.
Line#FS -6w
Line # is the number of the line the task is located.
The project settings must have dependencies enabled and the predecessor column identified.
This will not work if the project setting is not correctly set.
I hope this helps.
Frank Smith, PMP
Assistant Director | IT Special Projects Mgr.
Oregon Parks & Recreation Department
If my response helps, please mark it as an accepted answer. 😎
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives