Kia ora,
I am trying to show progress on on parent tasks over the year based on quarters, i.e.
Task 1 - Q1 = 59%, Q2 = 75%, Q3= 82%
Task 2 - Q1= 10%, Q2 = 45%, Q3= 56%
Task 3 - Q1= 100%
I have colour coded each quarter and am only wanting to to show the current quarter % complete in the graph, thus showing % complete to end of quarter for the task in total.
The problem I have is the graph keeps adding the %, so I thought I would have Q1 as % complete, Q2 as difference between Q1 and Q3 and then Q3 difference from 100 - The only issue I have with that is that it gives my "totals" label a small amount and not the correct amount. As well as it turns my axis at the bottom to numerical and not %.
Hope that explains my issue.
Thanks in advance.